DEMODemo only — use fictional data. Payments, bank connections, invoice delivery, and SMS verification are simulated.

Ironline Builders

Construct Ease Desk

PC-2026-009

Prime Contract — Two-Story Addition · Rivera Residence Addition · Rivera Family · signed Apr 21, 2026

Original contract value

$128,000.00

6 line items

Approved change orders

$0.00

0 applied

Revised contract value

$128,000.00

Previously invoiced

$73,000.00

57%

Remaining to invoice

$55,000.00

Schedule of values

Billing on any line is capped at its remaining amount.

CodeDescriptionTypeQtyUnit priceLine totalBilledRemainingProgress
03-300Foundation & concretelabor1 ls$30,000.00$30,000.00$30,000.00$0.00
100%
06-100Framing packagematerials1 ls$34,000.00$34,000.00$34,000.00$0.00
100%
07-300Roofing & weatherproofingmaterials1 ls$18,000.00$18,000.00$9,000.00$9,000.00
50%
08-500Windows & exterior doorsmaterials1 ls$16,000.00$16,000.00$0.00$16,000.00
0%
23-000Mechanical, electrical & plumbinglabor1 ls$20,000.00$20,000.00$0.00$20,000.00
0%
09-000Interior finisheslabor1 ls$10,000.00$10,000.00$0.00$10,000.00
0%
Contract total$128,000.00$73,000.00$55,000.00

Change orders

New change order
Change orderTitleStatusTotal
No change orders on this contract.

Invoices against this contract

InvoiceDateStatusNoteAmount
INV-1002Jun 30, 2026paidProgress billing #1 — foundation complete.$47,000.00
INV-1003Aug 28, 2026sentProgress billing #2 — framing complete, roofing 50%.$26,000.00